Manage

Add a new activity

An activity in the tree can for example be a project or a single task. To add a new activity to the tree do as follows:

  1. Click in the tree where you want to add a new activity.
  2. Click on the New button.
  3. An Activity dialog box is opened.
  4. Fill in the necessary information in the Activity dialog box.
  5. Click the Save button.

Edit an activity

By double clicking on an activity in the tree you can edit all information showed in the colums directly. If you would like to edit all fields for an activity select an activity and then click on the Edit button. The activity dialog box is then opened and you can edit directly in it.

Move

Use the cut/paste function to move an activity to another place in the tree. Do like this:

  1. Select the activity that you want to move by clicking on it.
  2. Click on the Cut button.
  3. Select the activity that you would like to move the task to.
  4. Click on the Paste button.

You may also move an activity using drag-and-drop.

Copy

Use the copy/paste function to copy an activity to another place in the tree. Do like this:

  1. Select the activity that you want to copy by clicking on it.
  2. Click on the Copy button.
  3. Select the activity that you would like to move the task to.
  4. Click on the Paste button.

Delete

Select an activity in the tree and click on the Delete button. Click Yes to delete the activity. Any subtasks will also be removed.

Set recurrance

This is the same as repeating a task.

  1. Select a task to repeat and click on the Set recurrance button.
  2. Edit the repeat option, start and end date.
  3. Press the Save button.